The plan for development and operation was approved in July 2010 and the field came on stream 2 April 2012.
The Marulk development consists of a well template with two gas production wells. The gas is produced by means of pressure relief and the well stream transported via a 30 km long pipeline to the Norne FPSO for processing.
The control cable and pipeline for the transport of hydraulic fluid and chemicals from the Norne FPSO to Marulk is relayed via the templates on the Alve field.
The processed gas is exported in the Åsgard Transport System to Kårstø and on to the European continent, while the condensate is delivered for sale via the Norne FPSO’s oil export facilities.
Operator: Eni Norge AS
Location: Block 6507/2, 6507/3, 6607/12, 6607/11 in the Norwegian Sea
Production start: April 2012
Production: Gas and condensate