Delayed production start at Njord after gas leak

April 25, 2011, 23:14 CEST
Bilde

The Njord-platform. Archive photo: Statoil

 


All production on Njord was immediately shut down and will remain shut down until the cause of the leak has been determined.

Production at the Njord field has been shut down since April 1 as a safety measure, while inspection of risers is carried out after earlier discoveries of internal damage to a particular type of flexible pipe.

The first instances of damage were discovered during a planned inspection last autumn, and an inspection programme was initiated which is now being carried out. Riser inspection is also being carried out at the Visund field.

Risers are the pipes that convey oil and gas from the seabed to the installation, and consist of several layers of plastic and steel. Production at Njord and Visund is planned to be phased in again in due course as inspection of the risers confirms that they are in order, or after they have been repaired or replaced.

The Njord field resumed partial production on April 16, but was shut down again on April 24 when manual measurements during a work operation revealed a gas leak from one of the risers after an automatic shutdown. The well was contained when the leak occurred.

The riser in which the leak was discovered was quickly depressurised, and production and the other risers were shut down in a controlled manner.

The Norwegian Petroleum Safety Authority (PSA) has been informed of the incident.

Shutdown delays production from the field. The total field production for Njord is around 70,000 barrels of oil equivalents (oe).

Risers on all installations are subject to constant monitoring and routine inspections in accordance with applicable inspection programmes.