Petrobras and Equinor start production on IOR project at Roncador, Brazil

Petrobras, the operator, and Equinor successfully started production from the first two wells of the increased oil recovery (IOR) project at Roncador.
This represents an important milestone in the development of the field, increasing recovery rates, adding valuable production and demonstrating the potential to leverage new technology.
The two wells are the first of a series of IOR wells to reach production. Start-up is almost five months ahead of schedule and at half of the planned cost. The wells add a combined ~20,000 barrels of oil equivalent per day to Roncador, bringing daily production to approximately 150,000 barrels and reducing the carbon intensity (emissions per barrel produced) of the field.
Through this first IOR project, the partnership will drill 18 wells, which are expected to provide additional recoverable resources of 160 million barrels. Improvements in well design and the partners’ combined technological experience are the main drivers behind the 50% cost reduction across the first six wells, including the two in production.
Roncador is Brazil’s fifth largest producing asset and has been in production since 1999. Petrobras is the operator of the field (75% equity) with Equinor (25% equity) entering the project in 2018 as a strategic partner.
We are very proud of what the partnership between Petrobras and Equinor has achieved, delivering this project ahead of schedule and below budget.

“This milestone demonstrates the partnership’s ability to increase production and value through technology. We will continue combining our capabilities to improve recovery from Roncador and extract further value from the field. Petrobras will leverage its experience as one of the largest deep-water operators and pre-salt developers in the world and Equinor will draw on its technology, expertise and decades of experience in IOR on the Norwegian Continental Shelf,” says Coelho.
In addition to the planned 18 IOR wells, the partnership believes it can improve recovery further and aims to increase recoverable resources by a total of 1 billion barrels of oil equivalent. The field has more than 10 billion barrels of oil equivalent in place, under a license lasting until 2052. The strategic alliance agreement also includes an energy efficiency and CO2 emissions reduction program for Roncador.
Latest news

Equinor contests penalty notice from Økokrim
In May 2021, Equinor Refining Norway AS (“Equinor Mongstad”) was charged with violations of the Pollution Control Act. The case concerns historical matters related to emissions and discharges that the company itself has uncovered, investigated, and improved.

Equinor's head office will remain at Forus
After a thorough process and evaluation of various alternatives, the Equinor board has decided to keep the head office at Forus East. The building will be significantly upgraded to create a modern, attractive and sustainable head office gathering all employees in the Stavanger region.

2024 tax contributions for Equinor
The tax contribution to society from Equinor amounted to a total of USD 25.8 billion for 2024, including employment taxes. In a year characterised by a gradual normalisation of energy markets, Equinor continues to deliver strong tax contributions.