Hammerfest LNG to resume operations in a week

The extensive repairs at Melkøya have been completed, but the run-up of the plant takes somewhat longer than planned.
During the weekend, a minor fault was discovered on a compressor that needs to be rectified prior to start-up. The component is now being replaced, and the stepwise process towards operations continues through the week.
"Hammerfest LNG has been prepared for production, but we are taking the extra time necessary to safely resume operations," says Grete B. Haaland, Equinor's senior vice president for onshore facilities.
Equinor announced on behalf of the partnership in January that the start-up of Hammerfest LNG had been scheduled for 17 May 2022. After an extensive repair and improvement work period, the plant has been prepared for ramp-up.
The partnership includes Equinor Energy AS, Petoro AS, TotalEnergies EP Norway AS, Neptune Energy Norway AS, Wintershall Dea Norway AS. Equinor is the operator of Hammerfest LNG.
Latest news
Equinor’s Energy Perspectives 2025
Energy Perspectives 2025 presents four scenarios for the future world economy, international energy markets and energy-related greenhouse gas emissions.
Strengthening UK energy security with new gas sales agreement
Equinor and Centrica sign long-term gas sales agreement of 55 TWh of natural gas per year (around 5 billion cubic meters - bcm) for a period of 10 years starting 1 October 2025 at terms reflecting market prices. The total contract value would be around £20 billion assuming current prices.
Election to Equinor's board of directors
In a meeting in the corporate assembly of Equinor ASA on 2 June 2025 Dawn Summers was elected as a new member of the board of directors of Equinor ASA.