Hammerfest LNG to resume operations in a week

The extensive repairs at Melkøya have been completed, but the run-up of the plant takes somewhat longer than planned.
During the weekend, a minor fault was discovered on a compressor that needs to be rectified prior to start-up. The component is now being replaced, and the stepwise process towards operations continues through the week.
"Hammerfest LNG has been prepared for production, but we are taking the extra time necessary to safely resume operations," says Grete B. Haaland, Equinor's senior vice president for onshore facilities.
Equinor announced on behalf of the partnership in January that the start-up of Hammerfest LNG had been scheduled for 17 May 2022. After an extensive repair and improvement work period, the plant has been prepared for ramp-up.
The partnership includes Equinor Energy AS, Petoro AS, TotalEnergies EP Norway AS, Neptune Energy Norway AS, Wintershall Dea Norway AS. Equinor is the operator of Hammerfest LNG.
Latest news
Equinor and Shell Announce CEO and Chair for Adura
Equinor and Shell announce the appointment of Neil McCulloch as Chief Executive Officer and Nicoletta Giadrossi as Chair of their offshore UK Incorporated Joint Venture, Adura.
Equinor to participate in Ørsted Rights Issue
Equinor has assessed the proposal put forward by the Board of Directors of Ørsted A/S on 11 August 2025 for a Rights Issue with pre-emptive rights for existing shareholders (the “Rights Issue”).
New oil and gas discovery near the Troll field
Equinor and partners have struck oil and gas in the Fram area, nine kilometres north of the Troll field in the North Sea.