Hammerfest LNG to resume operations in a week

The extensive repairs at Melkøya have been completed, but the run-up of the plant takes somewhat longer than planned.
During the weekend, a minor fault was discovered on a compressor that needs to be rectified prior to start-up. The component is now being replaced, and the stepwise process towards operations continues through the week.
"Hammerfest LNG has been prepared for production, but we are taking the extra time necessary to safely resume operations," says Grete B. Haaland, Equinor's senior vice president for onshore facilities.
Equinor announced on behalf of the partnership in January that the start-up of Hammerfest LNG had been scheduled for 17 May 2022. After an extensive repair and improvement work period, the plant has been prepared for ramp-up.
The partnership includes Equinor Energy AS, Petoro AS, TotalEnergies EP Norway AS, Neptune Energy Norway AS, Wintershall Dea Norway AS. Equinor is the operator of Hammerfest LNG.
Latest news

Invitation to send estimates for first quarter financial results
Equinor invites analysts with coverage of the company to provide estimates for the first quarter adjusted results.

Equinor partially divests shareholding in Scatec
Equinor ASA has divested an 8.07 percent shareholding in Scatec ASA at a price of NOK 125 per share.

Proposal on capital reduction from the company’s board of directors
The board of directors of Equinor ASA has today decided to propose to the general meeting of the company that the company’s share capital is reduced through cancellation of own shares and redemption of shares belonging to the Norwegian State.