Hammerfest LNG to resume operations in a week

The extensive repairs at Melkøya have been completed, but the run-up of the plant takes somewhat longer than planned.
During the weekend, a minor fault was discovered on a compressor that needs to be rectified prior to start-up. The component is now being replaced, and the stepwise process towards operations continues through the week.
"Hammerfest LNG has been prepared for production, but we are taking the extra time necessary to safely resume operations," says Grete B. Haaland, Equinor's senior vice president for onshore facilities.
Equinor announced on behalf of the partnership in January that the start-up of Hammerfest LNG had been scheduled for 17 May 2022. After an extensive repair and improvement work period, the plant has been prepared for ramp-up.
The partnership includes Equinor Energy AS, Petoro AS, TotalEnergies EP Norway AS, Neptune Energy Norway AS, Wintershall Dea Norway AS. Equinor is the operator of Hammerfest LNG.
Latest news
Developing the largest oil producer on the Norwegian continental shelf
Equinor and its partners are investing NOK 13 billion in the third phase of Johan Sverdrup, one of the world’s most carbon-efficient oil fields. New subsea infrastructure will increase recovery by 40–50 million barrels of oil equivalent (boe).
Oil discovery in the Johan Castberg area in the Barents Sea
Equinor has struck oil in exploration well 7220/7-CD-1H, Drivis Tubåen, on the Johan Castberg field in the Barents Sea.
Introducing Adura: The UK North Sea’s largest independent oil and gas producer
The name of the UK North Sea’s largest independent oil and gas producer has been revealed today, marking a major milestone in the creation of the new company.