Hammerfest LNG to resume operations in a week

The extensive repairs at Melkøya have been completed, but the run-up of the plant takes somewhat longer than planned.
During the weekend, a minor fault was discovered on a compressor that needs to be rectified prior to start-up. The component is now being replaced, and the stepwise process towards operations continues through the week.
"Hammerfest LNG has been prepared for production, but we are taking the extra time necessary to safely resume operations," says Grete B. Haaland, Equinor's senior vice president for onshore facilities.
Equinor announced on behalf of the partnership in January that the start-up of Hammerfest LNG had been scheduled for 17 May 2022. After an extensive repair and improvement work period, the plant has been prepared for ramp-up.
The partnership includes Equinor Energy AS, Petoro AS, TotalEnergies EP Norway AS, Neptune Energy Norway AS, Wintershall Dea Norway AS. Equinor is the operator of Hammerfest LNG.
Latest news

Equinor and Eneco sign 5-year gas agreement for supplies to the Netherlands
Equinor and Eneco have signed a 5-year agreement for deliveries of gas to Eneco, a main supplier of natural gas, electricity and heat in the Netherlands. The volumes are up to 0.5 billion cubic meters (bcm) per year with deliveries to the Dutch gas grid from 1 February this year.

Notifiable trading
Allocation of shares to certain primary insiders and their close associates in Equinor under Equinor's share savings plan.

Equinor fourth quarter and full year 2025 results
Equinor delivered an adjusted operating income* of USD 6.20 billion and USD 1.55 billion after tax* in the fourth quarter of 2025. Equinor reported a net operating income of USD 5.49 billion and a net income of USD 1.31 billion. Adjusted net income* was USD 2.04 billion, leading to adjusted earnings per share* of USD 0.81.