Adjusted assembly plan for the final four Hywind Tampen turbines

The seven first Hywind Tampen turbines will come on stream this year as planned. The final four will be installed next spring.
Supply chain bottlenecks, most notably related to the global market for steel, preclude delivery of the final four tower sections for the wind turbines until September 2022. This will be too late in relation to the installation weather window for the year, postponing installation of the remaining four turbines until next year.

“Seven turbines have been assembled and four are now installed on the field. The plan is to start production during the year and supply electricity first to Gullfaks, then to the Snorre field," says project director Olav-Bernt Haga.
Once Hywind Tampen is completed, it will be the world's largest floating wind farm and the first to supply electricity to oil and gas platforms. The wind farm has a system capacity of 88 MW and is expected to meet 35 per cent of the electrical power demand on the Gullfaks and Snorre fields. The seven first turbines will deliver electricity to both Gullfaks and Snorre and have a capacity of about 60 MW, already making Hywind Tampen the world’s largest floating wind farm.
Siemens Gamesa is the supplier of towers, nacelles and blades, all subject to rigid quality control measures. Deviations in steel quality in four tower sections were found, and corrective actions were immediately implemented. The difficult market situation for steel has however delayed delivery. Siemens Gamesa is working closely with their suppliers and Equinor to expedite all deliveries. The seven turbines already assembled have been thoroughly tested and meet all quality specifications.
Latest news

Equinor makes new discoveries in the North Sea
Equinor has made two new discoveries of gas and condensate in the Sleipner area of the North Sea. These are Equinor’s largest discoveries so far this year and can be developed for the European market through existing infrastructure.

Rapid development extends the lifetime of Norne
On 2 December production started from the Verdande subsea field in the Norwegian Sea. The field is tied back to the Norne FPSO. With reserves of 36 million barrels of oil, Verdande helps extend Norne’s production beyond 2030.

Equinor and Shell complete formation of Adura
Equinor and Shell have completed a deal to combine their UK offshore oil and gas operations to form a new company. Adura, which launched today, will be the UK North Sea’s largest independent producer.