Peering down from an airplane at icebergs scattered off Newfoundland's craggy coastline, it seems fitting that the descendants of Vikings who landed here a millennium ago now play an integral role developing eastern Canada's emerging offshore industry.
Hydro's part includes an alliance with operator Petro-Canada, lending technical assistance based on 25 years of developing and operating oil and gas projects in precarious Norwegian waters.
The alliance's immediate task is finishing the Terra Nova field development project – the world's first to deploy an floating production storage and offloading (FPSO) vessel in harsh, iceberg-prone waters – set to start producing this autumn.
Nearing completion
Terra Nova is nearly complete, Petro-Canada's field asset manager Gordon Carrick said during a tour of the project's FPSO at Bull Arm construction site in Newfoundland in mid June.
The last tasks to be finished are drilling and reservoir, subsea and marine operations, hook-up and completion, and operations readiness. After concluding sea trials in nearby Trinity Bay, the ship recently sailed to the field for offshore commissioning activities in preparation for a production start-up in early fall.
"The plan calls for introducing hydrocarbons in late September or early October and then starting deliveries in mid-October," says Hydro's vice president for offshore development and operations, Lars Andreas Sunde.
Five of six initial wells are already drilled and operations will "quickly ramp up" from about 80,000 barrels per day (bpd) by the end of this year to about 130,000 bpd in late 2002, Carrick reports, adding "so far, our wells have met expectations."
A total of 24 wells – 14 producers, seven water injection and three gas injection wells – will be drilled during the field's planned 15-year lifetime.
Terra Nova is estimated to hold more than 400 million barrels of recoverable oil and has potential for another 100 million barrels in an undrilled adjacent block.
Full sail
Once fully operational, the FPSO's control room will handle most tasks, says Eric O'Brien, one of the ship's two alternating captains assigned to command a full-time crew of 49, and who has "seen seven continents" during his lengthy maritime career.
"The bridge will be a good place to read a book after everything's operational," quips his colleague, production leader Lee Braithwaite.
"A lot of people ask, 'Won't you get bored not going anywhere?' I tell 'em there'll be plenty to do," O'Brien replies.
Double-hulled and built with 3,000 tons of extra steel to protect it from renegade icebergs, the FPSO has five dynamic positioning units with 100 tons of thrust each. The dual satellite-guided DP system can "actually ask the ship to move as little as 10 centimeters," O'Brien explains. Together with heavy anchor chain secured to the seabed, the ship will "only deflect 1.5 meters in a 100-year storm."
The FPSO, which has the world's largest disconnectable turret, can produce up to 150,000 bpd and has a 960,000-barrel storage capacity, Braithwaite adds.
Making up lost time
The most challenging part of the project has been hook-up and commissioning, Carrick says, indirectly referring to delays and cost-overruns confronted after the FPSO arrived at Bull Arm in May 2000.
Originally slated to start producing in late 2000, extra time was required to perform remedial work resulting from late and incomplete engineering and quality problems identified in vessel and topsides modules. An estimated 500,000 man-hours initially planned to complete the FPSO have subsequently soared to 2 million hours in the budget update in February 2001. The original budget of CAD 2.1 billion (EUR 1.6 billion) will likely end up at around CAD 2.7 billion (EUR 2.09 billion).