Initial field development contracts had been signed before Hydro's plan for development and operation (PDO) for the Fram East satellite field in the North Sea was submitted to Norways Ministry of Petroleum and Energy. From boring of wells through pipeline tie-in and new Troll C processing infrastructure, the Fram East development project will cost an estimated NOK 4.6 billion.
Fram East will be developed as a satellite field, using two well-head templates installed on the seabed, in waters 360 meters deep. The wellstream will be piped 20 kilometers south for processing at the Troll C platform along with oil from Fram West.
âBecause Fram East production is scheduled for 31 October 2006, every stage of development is extremely time-critical,â says Bjørn Hjermann, Fram East Development project leader.
âBy that date, all subsea installations and pipelines must be finished, modifications to the Troll C platform must be completed, and wells must be producing.â Hjermann continues, âTo meet the tight deadline weâve picked tested solutions and proven technologies.â
Three major contracts signed
Kvaerner Oilfield Products was awarded the first Fram East development contract in December 2004 for the fieldâs subsea equipment.
In February, two more major contracts were entered into. The contract for modifications to Troll C processing facilities was awarded to Aker Kvaerner Offshore Partner AS, and Leirvik Module Technology signed a contract to expand the Troll C housing module, increasing its capacity from 70 to 100 beds for platform crews.
âThe Ministry of Petroleum and Energy hasnât objected to our awarding several contracts before submitting the PDO,â Bjørn Hjermann notes. âItâs vital to start field work as planned; itâs in everyoneâs interest that Troll area infrastructure is utilized in the best way.â
Typical next-generation approach
Fram East is representative of the way many upcoming North Sea licenses will be developed. These are marginal fields for which independent field development is not commercially viable.
âAs a satellite field of the Troll C platform, however, the Fram East field will become a valuable resource that makes efficient use of the existing infrastructure,â Hjermann explains.
Field development gets underway in June, with installation of the two subsea templates. In the summer of 2006, two pipelines and a control cable will be laid to connect the well-head templates to the Troll C platform.
Drilling begins this autumn and will continue until the autumn of 2006, with an 11 week interruption during the summer of 2006 when the pipelines and control cable will be laid.
âFields such as Fram East represent the future on the Norwegian Continental Shelf. Linking of subsea production units to larger-sized platforms is occurring more frequently,â comments Johan Kr. Mikkelsen, the chief of Oil & Energy's Troll business area, which includes the Fram region.
According to Mikkelsen, once Fram East field development is completed, both water and gas injection will be available for Fram reservoir management. âFuture development projects will benefit from this infrastructure,â he points out.
Mikkelsen praises the Fram partners for excellent cooperation and their contributions that allow for adaptable development. âOur field development plan can be readily expanded. Fram East infrastructure can be extended easily, and at low cost, by adding two more templates to exploit other Fram structures,â Mikkelsen says.
| Fram East facts
|
| Partners | |
| Hydro (operator) | 25 % |
| ExxonMobil | 25 % |
| Statoil | 20 % |
| Gaz de France | 15 % |
| Idemitsu | 15 % |