Government go-ahead for Irpa, Verdande and Andvare

The plans for development and operation of the subsea fields Irpa and Verdande, and the production well Andvare in the Norwegian Sea have been approved by Norwegian authorities. The gas field Irpa will be tied back to Aasta Hansteen, whereas the oil field Verdande and the Andvare well will be tied back to Norne.
"We are experiencing a strong demand for oil and gas from the Norwegian continental shelf in the current geopolitical situation. By utilising the Aasta Hansteen and Norne infrastructures, these development projects will quickly bring new production to market with low development costs, while extending the activity on the host platforms," says Trond Bokn, Equinor's senior vice president for project development.

The Irpa gas volumes may supply just over 2.3 million UK households with gas for seven years. The gas discovery is located almost 80 kilometres from the Aasta Hansteen field, and the development will extend the field’s productive life by seven years, up to 2039. The discovery also supports the 350 person-years of employment (direct and indirect) associated with the operation of Aasta Hansteen during this period.
Irpa, the second subsea field tied back to Aasta Hansteen, will be the deepest field on the Norwegian continental shelf, at 1350 metres.
It was recently announced that Westcon Helgeland will deliver large parts of the Irpa subsea facility as a TechnipFMC subcontractor. Momek in Mo i Rana is a subcontractor of Aibel, responsible for modifying the platform for Irpa gas tie-in.

Verdande, an oil discovery with some associated gas, will be tied back to Norne. Here, too, the field’s productive life will be extended by several years, which helps support the 900 person-years of employment (direct and indirect) associated with the operation of the Norne field.
Equinor, on behalf of the partners, recently awarded a contract to Aibel where most of the work will be performed by Aibel's M&M community in Harstad, which will also use other subcontractors in the north. Aibel will also make modifications to the FPSO related to Andvare, a well that will be drilled as a side-track from one of the existing subsea templates on the Norne field.
“For Equinor and our partners, it is important that our activity in the north also has ripple effects here, and the projects will also result in increased and prolonged activity at the logistics base in Sandnessjøen and the helicopter base in Brønnøysund," says Bokn.
The Ministry of Petroleum and Energy today celebrated the approval of a number of new projects on the Norwegian continental shelf. In addition to being the operator of Irpa, Verdande and Andvare, Equinor is also a partner in Yggdrasil, Berling, Skarv Satellitter and Symra.
Latest news

Equinor's head office will remain at Forus
After a thorough process and evaluation of various alternatives, the Equinor board has decided to keep the head office at Forus East. The building will be significantly upgraded to create a modern, attractive and sustainable head office gathering all employees in the Stavanger region.

2024 tax contributions for Equinor
The tax contribution to society from Equinor amounted to a total of USD 25.8 billion for 2024, including employment taxes. In a year characterised by a gradual normalisation of energy markets, Equinor continues to deliver strong tax contributions.

Investing in the next phase at Johan Castberg
Equinor, Vår Energi and Petoro will invest just over NOK four billion in the first discovery tied back to the Johan Castberg field in the Barents Sea. The decision was made eight months after Johan Castberg came on stream.