Gas leaks on Sleipner field stopped – parts of the field are shut down

A gas leak in a contained area related to a turbine on Sleipner A was reported in the morning of 11 July. The incident was quickly clarified.
During the process of resuming production and depressurisation, an additional gas leak occurred on the Sleipner R riser platform late Monday night.
Personnel on board mustered according to procedure in both situations, but they were demobilised shortly afterwards. No personnel were injured in any of the incidents.
Work is ongoing to safely resume normal operation.
The authorities have been notified and the incidents will be further investigated to find the causal relation.
Latest news
Equinor and Shell Announce CEO and Chair for Adura
Equinor and Shell announce the appointment of Neil McCulloch as Chief Executive Officer and Nicoletta Giadrossi as Chair of their offshore UK Incorporated Joint Venture, Adura.
Equinor to participate in Ørsted Rights Issue
Equinor has assessed the proposal put forward by the Board of Directors of Ørsted A/S on 11 August 2025 for a Rights Issue with pre-emptive rights for existing shareholders (the “Rights Issue”).
New oil and gas discovery near the Troll field
Equinor and partners have struck oil and gas in the Fram area, nine kilometres north of the Troll field in the North Sea.