Investing in Hywind Tampen development

October 11, 2019 06:54 CEST | Last modified August 10, 2021 13:27 CEST
Submission of PDO to prime minister Erna Solberg
State secretary Rikard Gaarder Knutsen (left) and prime minister Erna Solberg received the PDOs from Arne Sigve Nylund, executive vice president for Development & Production Norway, and Pål Eitrheim, executive vice president for New Energy Solutions.
(Photo: Ole Jørgen Bratland)

Equinor and the Snorre and Gullfaks partners have made a final investment decision for the Hywind Tampen offshore wind farm development. Today, two updated plans for development and operation will be submitted to Norwegian authorities.

Illustration of Hywind Tampen
Illustration of the Hywind Tampen project. Dimensions and distances are not realistic.

The oil and gas platforms will be the first ever powered by a floating offshore wind farm. The wind farm will be located some 140 kilometres from shore in 260-300 metres of water between the Snorre and Gullfaks platforms.

“We have been systematically maturing technologies for floating offshore wind for almost 20 years. The decision by the Snorre and Gullfaks partners helps bring this technology an important step forward. About 80 % of the global resource potential for offshore wind is in deep waters, and floating offshore wind may play an important part in the energy transition towards more sustainable global energy supply. This brings substantial opportunities for Norwegian industry,” says Eldar Sætre, chief executive officer of Equinor.

The Hywind Tampen investments will total almost NOK 5 billion. Norwegian authorities through Enova have made a funding commitment of up to NOK 2.3 billion for the Hywind Tampen project. In addition, the Business Sector’s NOx Fund has decided to support the project by up to NOK 566 million.

The wind farm will consist of 11 wind turbines based on the Hywind technology developed by Equinor. The 8 MW turbines will have a total capacity of 88 MW, capable of meeting about 35 percent of the annual electricity demand of the five Snorre A and B, Gullfaks A, B and C platforms.

Photo of Eldar Sætre (left) and Arne Sigve Nylund
Chief executive Eldar Sætre (left) and Arne Sigve Nylund, executive vice president for Development & Production Norway.
(Photo: Ole Jørgen Bratland)

“The pioneering Hywind Tampen project will help cut emissions from Gullfaks and Snorre. We are driving a transition aimed to sustain and add value on the Norwegian continental shelf, while reducing the carbon footprint from our operations,” says Arne Sigve Nylund, Equinor’s executive vice president for Development & Production Norway.

By reducing the use of gas turbines on the fields the project helps cut CO2 emissions by more than 200,000 tonnes per year.

“The authorities’ consent to extending the productive life of the Gullfaks field to 2036 and the Snorre field to 2040, up to 20 years longer than when the fields were initially planned, has been essential to realizing the Hywind Tampen project,” says Nylund.

According to a study performed by Multiconsult the Hywind Tampen project will generate 1550 to 3000 man-years through the field’s productive life in spin-offs for Norwegian industry. Most of the spin-offs will be generated in the project’s development phase.

Scheduled to come on stream in late 2022 Hywind Tampen will be operated from Equinor’s Bergen office. Gulen Industrihamn in western Norway has been chosen for the assembly of the floating wind turbines for Hywind Tampen before being transported to the field in the North Sea.

Submission of plan for development and operation

The press is invited to the PDO handover event at Equinor’s office at Fornebu, the main entrance Friday 11 October at 13:00 hrs.

Prime Minister Erna Solberg will be present. Executive vice presidents Pål Eitrheim and Arne Sigve Nylund will hand over the PDO’s on behalf of the partners.

For questions, please contact vice president Media Relations, Bård Glad Pedersen, bgp@equinor.com, phone +47 91801791.

Please sign up for participation to Elisabeth Bruksås, elbru@equinor.com 

Partners:

  • The Gullfaks licence: Equinor Energy AS:  51 %, Petoro AS:  30 %, OMV (Norge) AS:  19 %
  • Snorre licence: Equinor Energy AS: 33,3 %, Petoro AS: 30 %, ExxonMobil Exploration and Production Norway AS: 17,5 %, Idemitsu Petroleum Norge AS: 9,6 %, DEA Norge AS: 8,6 %, Vår Energi AS: 1,1 %