The Njord field upgraded and ready for another 20 years

Production from the Njord field in the Norwegian Sea resumed at 16.30 on 27 December, following an upgrading project in which both the platform and the floating storage and offloading vessel (FSO) were brought ashore.
The field is now back on stream, ensuring secure and stable energy supplies to Europe.
Both the platform and the FSO have undergone extensive upgrades, and the project has a Norwegian content of more than 90 percent. Aker Solutions has had the main responsibility for the platform engineering and upgrading. Brevik Engineering has carried out the engineering work for the FSO, which has been upgraded by Aibel.

“I am proud that we and our partners, Wintershall Dea and Neptune Energy, have now got this truly unique project across the finish line. This is the first time a platform and a FSO have been disconnected from the field, upgraded, and towed back, and we have now doubled the field’s life.It has been a big and challenging job, partly performed during a pandemic, and I want to thank everyone who has contributed. The Njord field will now deliver important volumes to the market for another two decades," says Geir Tungesvik, Equinor's executive vice president for Projects, Drilling & Procurement.
Coming on stream in 1997, the Njord installations were initially designed to remain in operation until 2013. However, there were large volumes left in the ground, in addition to discoveries nearby, such as Hyme which came into operation in 2013, and others that can be produced and exported via Njord.
The platform and FSO were brought ashore in 2016 after 19 years of production. In 2017 and 2018, upgrading contracts were awarded for the two installations. The Njord A platform was upgraded at Stord, where it was constructed in the 90s. The Njord Bravo FSO was inspected prior to upgrade and prepared for tow-out in Kristiansund, whereas the refurbishment was carried out in Haugesund.

“Our ambition is to produce about the same volume from Njord and Hyme as we have produced so far, more than 250 million barrels of oil equivalent," says Kjetil Hove, Equinor's executive vice president for Exploration & Production Norway.
10 new wells will be drilled at Njord from an upgraded drilling facility, new discoveries have been made at the outer edges of Njord, and more exploration will be carried out in the surrounding area.In addition, the platform and FSO have been prepared to receive production from two new subsea fields, Bauge and Fenja, with a total of 110 million barrels of recoverable resources.
“This is illustrative of our strategic work on the NCS to extend the fields’ productive life and tying back new discoveries to existing infrastructure, while reducing the climate footprint from the production," says Hove.
According to plans the Njord field will in a few years receive power from shore via the Draugen platform in the Norwegian Sea and be partially electrified. This will reduce the annual CO2 emissions by about 130,000 tonnes.
Production from the Njord field was initially supposed to resume two years ago. However, the upgrading project has been more challenging than expected, and the project was hard hit by the Covid-19 pandemic. This has also put an upward pressure on costs. Capital expenditures total just over NOK 31 billion (2022), compared with the original NOK 17 billion in the plan for development and operation.However, the project is profitable with oil prices far lower than today.
Accept Cookies
Want the full picture? We’d love to share this content with you, but first you must accept marketing cookies by enabling them in our cookie settings.
Latest news
Stop work order lifted, Empire Wind project resumes construction
Empire Offshore Wind LLC (Empire), a subsidiary of Equinor ASA, has been informed by the Department of the Interior’s Bureau of Ocean Energy Management (BOEM) that the stop work order has been lifted for the Empire Wind project, allowing construction activities to resume.
Ex. dividend fourth quarter 2024
The shares in Equinor ASA will be traded on the Oslo Stock Exchange (OSE) and New York Stock Exchange (NYSE) exclusive the fourth quarter 2024 cash dividend as detailed below.
Minutes from the annual general meeting 2025
On 14 May 2025, the annual general meeting in Equinor ASA approved the annual report and accounts for Equinor ASA and the Equinor group for 2024, as proposed by the board of directors.